Bangladesh's Public Private Partnership Authority listed 81 projects in its portfolio as last updated on 19 August 2026, of which four were in operation (including Patenga Container Terminal, the NIKDU and Chittagong haemodialysis centres and two Info-Sarkar 3 rural broadband components), three were partly operating while still under construction (among them the Dhaka Elevated Expressway), and 10 were under construction.
7 of 81 portfolio projects (4 operational, 3 partial operation and construction), ppp projects in operation, fully or partly, 2026-08-19. 10 projects, ppp projects under construction, 2026-08-19. Public Private Partnership Authority Bangladesh, PPP projects list, retrieved 2026-10-02.
The move, and what it needed
A dedicated authority under the head of government screens line-ministry projects, runs procurement with technical assistance and viability gap funds, and takes them to the economic cabinet committee for approval and award.
Preconditions
- A PPP law (2015) and rules for viability gap funding and unsolicited proposals
- Line ministries willing to give up projects they could fund from the development budget
- Investors willing to take Bangladeshi currency and land risk, which is the precondition the low operating count suggests is scarce
Limits: The counts are ours, tallied from the stage column of the authority's project list, which the page says was last updated on 19 August 2026 and which was read on 2026-10-02; the page gives no totals, and it reports stages, not dates of financial close or of operation. Two of the four operating entries are components of one rural broadband project (Info-Sarkar 3), so the operating count overstates distinct partnerships by one. The authority promotes its own portfolio. The headline is how little has reached operation: 7 of 81 projects after some 16 years, with 24 still at feasibility study and 6 at conditions-precedent stage, so the record documents scale of activity more than delivery. Several listed projects are land leases for commercial development (shopping malls, textile mills on state land), not public services. The Dhaka Elevated Expressway opened in parts against long delays. A 2026 Invest Bangladesh Act appears on the same site and may reorganise the authority; its Bangla text could not be read in this session, so the record does not say whether the authority continues in its current form.