Collaborative Research and Innovation Grant Scheme (CRIGS)
The Mauritius Research and Innovation Council's Collaborative Research and Innovation Grant Scheme, which co-funds projects led by a local company with a local academic or research institution, had completed 17 projects and had 14 more under way as at 30 June 2020, with 61.5 million rupees of private contribution to the completed ones.
17 projects, crigs projects completed (project value rs 115.9 m, private sector contribution rs 61.5 m, mric amount rs 53.4 m), cumulative to 30 June 2020. 14 projects, crigs projects ongoing (project value rs 102.18 m, private sector contribution rs 57.22 m), 30 June 2020. Mauritius Research and Innovation Council, Annual Report September 2019 to June 2020, Portfolio section, retrieved 2026-10-02.
The move, and what it needed
The national research council pays roughly half the cost of an R&D project only when a registered company applies with a local university or research institute as partner, so public money follows a firm's own commitment.
Preconditions
- A national research and innovation council with a competitive grant budget
- A university and research institute base able to take on contract work for local firms
- Firms large enough to co-fund half of a multi-million rupee project
Limits: The council reports on its own scheme. The figures sit in a PDF on page 23 of 66 (printed page 22); the portfolio table on the same page gives a different split for the reporting year alone (10 ongoing and 3 completed CRIGS initiatives), so the cumulative and annual counts must not be mixed. 2019-20 is the latest annual report the council has published: its publications page lists the 2020-21 to 2023-24 reports as awaiting audit or in process, so nothing after June 2020 can be checked against an annual report. The scheme page (mric.mu/collaborative-research-and-innovation-grant-scheme) still describes the scheme and lists 18 funded projects, all marked completed, with no ongoing project and no call dates, so the scheme may have funded little or nothing since 2020; 'operating' rests on the page still offering it and is the weakest part of the record. Thirty-one projects over six years is small even for a country of 1.3 million people, the counts are projects rather than distinct firms, and project value includes the firm's in-kind contribution. The start year is the first call for proposals, June 2014, stated in the council's Annual Report 2014, not at the cited URL. Nothing here shows the research results or commercial outcomes.