Documented examples

Each record describes something a country built that the indicators do not capture. The source provides the published number; the mechanism is our interpretation.

Scores describe outcomes. These records describe how a country acted, what it needed and what happened. 742 of 742 records include a mechanism. They do not affect scores.

Narrow the list

2 of 742 deliveries

Adaptability

1 delivery linked to Disaster preparedness and recovery.

Tajikistansince 1998delivered and closedbears on Disaster preparedness and recovery

Emergency Flood Assistance Project after the 1998 and 1999 floods

After floods in 1998 caused damage estimated at US$40 million, about 2 percent of GDP, Tajikistan's Republican Project Coordination Unit for Liquidation of Consequences of Natural Disasters had repaired about 210 km of roads and fully completed seven bridges and structures by the credit's closing on 31 December 2001, with about 80 km of road repairs and three bridges unfinished, and the World Bank rated the outcome unsatisfactory.

210 km, road repairs completed at closing (about 80 km more unfinished), 2001-12-31. 40 million US dollars, damage from the 1998 floods as estimated, 1998. World Bank, Implementation Completion Report, Tajikistan Emergency Flood Assistance Project (IDA-31230, IDA-31231), Report No. 24209, 2002, retrieved 2026-10-02.

The move, and what it needed

A government emergency coordination unit repaired flood-damaged bridges, roads and embankments with an emergency IDA credit through local contractors, without the supervision capacity to hold them to quality.

Preconditions

  • An emergency lending window that disburses within months
  • Local contractors with experience of the work, which were scarce after the civil war
  • A coordination unit with financial controls the lender trusts, which it lacked

Limits: The World Bank wrote the report and rated the outcome Unsatisfactory and sustainability Unlikely, mainly over poor works quality and financial management; it refused a further extension and closed the credit as planned. The record is filed as evidence of weak recovery capacity, not of success. The report says the roads actually damaged totalled about 105 km of the 210 km repaired, that works quality was poor because local firms lacked experience and supervision, and that only three of eight planned power substations were completed. The project came a year after the end of a five-year civil war, with a supplemental credit after further floods in 1999, so capacity was at a low point. The text is OCR of a scanned 2002 report, and the data sheet and narrative disagree on the original closing date (January 2000 against June 2001).

Building

1 delivery linked to Large project delivery.

Tajikistansince 2007still operatingbears on Large project delivery

Rogun hydropower plant

The Government of Tajikistan resumed construction of the Soviet-era Rogun hydropower plant in 2007 from the state budget, signed the main dam contract in 2016 and commissioned two temporary units (400 MW) in 2018 and 2019. It invested about US$3.3 billion in 2007 to 2022, and in November 2024 the World Bank put the cost to complete the plant at US$6.29 billion, with construction completion moved to 2033 and full reservoir impoundment not before 2039, 63 years after construction first began in 1976.

6.29 billion USD, estimated cost to complete the rogun hpp programme, November 2024. 3.3 billion USD (about), government of tajikistan investment in rogun hpp, 2007 to 2022, 2007-2022. World Bank, Project Appraisal Document PAD00208, Sustainable Financing for Rogun Hydropower Project (P181029), 19 November 2024, retrieved 2026-10-02.

The move, and what it needed

The Tajik government restarted a stalled Soviet megaproject from its own budget and a Eurobond, brought two temporary turbines online early to earn revenue during construction, then used World Bank-backed safety and environmental studies to draw in a donor financing package for the rest.

Preconditions

  • A site with Soviet-era works, surveys and tunnels already in place
  • A state willing to divert a large share of GDP to one project for over a decade
  • Riparian water agreements and an independent dam-safety review credible enough for international lenders

Limits: No cost overrun can be computed: the appraisal document gives no original budget or baseline completion date to set the US$6.29 billion against, so the gap's unit (percent overrun) is not met. The US$6.29 billion is a forward estimate of remaining cost with contingencies, not an outturn, and adding it to the US$3.3 billion already spent is our arithmetic, not the Bank's. The schedule slip is our reading of milestone dates: construction began in 1976, the Soviet works stopped in 1992, and completion is now 2033 with impoundment in 2039. The Bank itself expects 'some further delays' to the March 2024 milestones. It attributes slow progress to financing shortfalls. The source is the lender's appraisal for its own grant, written to justify financing. The project is now financed by ten development partners, so delivery after 2024 is shared rather than purely Tajik. Spending close to 39 percent of GDP and a US$500 million Eurobond left the country at high risk of debt distress. 'Operating' means two temporary units run, not that the 3,780 MW plant is built.