Egypt, building

Ain Sokhna supercritical power plant

The Egyptian Electricity Holding Company built the 1,300 MW Ain Sokhna supercritical thermal power plant, with its first unit entering commercial operation on 3 March 2015 and the second on 4 June 2015, at a final cost of US$1,159.4 million against a base cost of US$2,139.6 million estimated at appraisal in 2009.

Egyptsince 2009still operatingbears on Large project delivery

1,159.4 million US dollars, final cost of the ain sokhna power plant component, 2019-03. 2,139.6 million US dollars, base cost of the power plant component at appraisal (pad), excluding us$50.2 million contingencies, 2009. World Bank, Implementation Completion and Results Report, Egypt Ain Sokhna Power Project (P100047), 26 June 2019, retrieved 2026-10-02.

The move, and what it needed

The state power holding company procured a large thermal plant in a few big packages co-financed by four lenders, priced the appraisal estimate conservatively, and redeployed the savings into grid works.

Preconditions

  • A state utility with an engineering department experienced in large thermal plants
  • Co-financing from several development lenders committed before bidding
  • A market for supercritical boilers and turbines competitive enough to bid below estimate

Limits: The World Bank, which lent US$600 million of the cost, wrote the report. The costs are in Table 1 and para. 23 (ICR pages 8 to 9), the commercial operation dates in para. 20 of the annex on design and implementation; the report says construction was 'initially delayed' but finished 'about when expected' and gives no original target date for commercial operation, so schedule performance rests on that judgement and on the 2015 dates. The ICR does not explain why the plant cost 46 percent less than estimated; a 2013 restructuring had already cut the estimate to US$1,655.3 million, which suggests the 2009 estimate was high rather than that delivery was unusually efficient, and the savings went into a transmission component. That transmission component ran late: it was not finished at the extended loan closing of 31 December 2018 (original closing 31 December 2015), and its final cost was not known. The plant was designed to burn heavy fuel oil as well as gas, which the report says raised its cost and lowered its efficiency against a combined-cycle plant. The status rests on the report's account of operation in 2015 to 2018, not on a current source.

This record describes what Egypt delivered. It is linked to Large project delivery because no comparable dataset measures that capability. It does not affect the score or confidence.

More from Egypt

3 other deliveries from this country.

  • Takaful and Karama cash transfer programme

    Egypt's Ministry of Social Solidarity launched the Takaful and Karama cash transfers in early 2015 and expanded coverage from an initial 1.5 million to 4.675 million households (about 17 million people) by project close in 2024, revising the eligibility threshold and adding top-ups in response to COVID-19 and later inflation, while the cash transfer budget rose from EGP 3.5 billion in 2015 to EGP 41 billion in 2024.

  • Renewable energy feed-in tariff programme and Benban

    Egypt's Ministry of Electricity and Renewable Energy took private sector-owned renewable generation from 0 MW in October 2015 to 1,500 MW at financial closure by the end of FY2017/18 under its feed-in tariff programme, with about US$2 billion of private investment, much of it in the Benban solar park.

  • COVID-19 vaccination campaign

    Egypt's health authorities reported to WHO that 56,907,319 people, 56 per 100 population, had received at least one COVID-19 vaccine dose by 31 December 2023, from a first dose given on 24 January 2021, with 42,337,175 (41 per 100) completing the primary series.

Every delivery from Egypt

The same indicator elsewhere

181 deliveries linked to Large project delivery in other countries.

  • Pix instant payment system

    Brazil's central bank specified, built and ran a mandatory instant payment rail that settled 7.98 billion transactions in July 2026, for 152 million people and 14 million firms transacting in that month.

  • GOV.BR federal identity and service platform

    Brazil consolidated federal public services behind one identity platform, reporting 175 million active accounts and 5,179 digital services in May 2026.

  • X-Road national data exchange layer

    Estonia has run one data exchange layer for the whole state since 2001, and in July 2026 it carried 374.9 million queries between 1,000 connected organizations, 251 of them government bodies, across 3,785 services.

  • Pradhan Mantri Jan Dhan Yojana bank accounts

    India opened 590.9 million basic bank accounts through existing banks from 2014, holding 3.17 lakh crore rupees in deposits as of 19 August 2026.

  • Electricity supply rebuilt on renewable sources

    Uruguay rebuilt its electricity supply between 2010 and 2017 through public tenders and long-term contracts, and in 2025 fossil fuels produced 293 GWh of the 15,855 GWh generated, so 98.2 percent came from hydro, wind, biomass and solar.

  • Plan Ceibal, one connected laptop per child

    Uruguay gave a connected laptop to every child in public primary school from 2007, the first country to do it nationally, and the household survey found a Ceibal computer in the homes of 35.8 percent of the population in 2018.

  • Sistema Unico de Saude, universal public health system

    Brazil wrote a right to health into the 1988 constitution and built a single public system that covers everybody in the country, and the WHO service coverage index for Brazil rose from 71 in 2000 to 84 in 2023.

  • Programa Nacional de Imunizacoes, and its erosion

    Brazil's national immunisation programme reached 99 percent DPT coverage in 2003 and held above 95 percent for a decade, then fell to 68 percent by 2021 and had recovered to 91 percent by 2024.

  • Luz para Todos, rural electrification

    Brazil connected the last rural households to electricity through a national programme run with the state and private distributors, taking access from 94.4 percent of the population in 2000 to 99.8 percent in 2024.

  • Bolsa Familia and the single registry behind it

    Brazil built one national registry of low-income households and paid conditional transfers through it, going from 6.6 million benefits in December 2004 to a peak of 21.0 million in 2022 and 18.6 million in December 2025.

  • Fully electronic national elections

    Brazil has run every election on electronic voting machines since 2000, across an electorate that reached 155.9 million voters in 2024, with results published the same evening.

  • Deepwater and pre-salt oil production

    Brazil developed deepwater extraction, found the pre-salt fields in 2006 and produced them at depths of more than 5,000 metres, with national oil production rising from 71,844 thousand cubic metres in 2000 to 219,032 in 2025.

  • Seguro Popular, and its abolition

    Mexico built public health insurance for people outside social security from 2003 and abolished it in 2020, and CONEVAL measured the share of the population without access to health services rising from 16.2 percent in 2018 to 39.1 percent in 2022.

  • Sure Start children's centres, and their erosion

    England built a national network of early-childhood centres reaching 3,632 sites by August 2009, then closed or hollowed out a large part of it after funding was cut, with the official count at 3,123 by October 2017 and independent estimates near 1,000 closures.

  • Grid power, and load shedding

    South Africa ran one of the world's cheapest reliable grids and extended it to most of the population after 1994, then under-invested and lost the surplus, reaching 335 days of load shedding in 2023 before recovering to 83 days in 2024.

  • Measles elimination, and its erosion

    The United States eliminated endemic measles transmission by 2000 through school-entry vaccination requirements, and falling coverage brought 2,777 confirmed cases by August 2026, the most since 1991, against 285 in all of 2024.

  • BNDES, the national development bank

    Founded in 1952, Brazil's federal development bank provides long-term financing and investment across the national economy, and it disbursed R$169.7 billion in 2025.

  • Casa da Moeda do Brasil, the national mint

    Founded in 1694, Brazil's national mint has remained a public institution through colonial, imperial and republican regimes and now produces currency, identity documents and passports after more than 330 years of operation.

  • Housing and Development Board, public housing at scale

    Singapore set up the Housing and Development Board in 1960 to address a severe housing shortage, and it built more than 21,000 flats within its first three years.

  • AFE passenger rail and network contraction

    Uruguay's state railway suspended passenger service in January 1988 to focus on freight; by 1990 about half of the national network had been declared non-operational, leaving 1,484 kilometres active from a 2,998-kilometre network, before passenger services returned only partially in 1993.

  • Flamanville 3 EPR, and the erosion of nuclear new-build delivery

    France's Flamanville 3 EPR took about 16.5 years from construction beginning in September 2007 to completion in early 2024, and its commissioning was the country's first new nuclear reactor since Civaux 2 in 1999, a 25-year gap.

  • Phoenix pay system, and its prolonged failure

    Canada rolled out the Phoenix federal pay system in 2016, then spent more than C$2.6 billion by April 2022 to support and stabilise it and correct pay-file errors, with a further roughly C$1 billion allocated through the 2024-25 fiscal year.

  • Groningen gas system, and its closure after induced earthquakes

    The Netherlands ended roughly sixty years of Groningen gas extraction with the permanent closure of all production locations on 19 April 2024; by the end of 2024 the response system had handled more than 500,000 damage reports and paid over €2.5 billion in compensation.

  • DigiD, a shared digital identity rail for public services

    The Netherlands has run DigiD as a shared login for public services since 2005; in 2024 it recorded 550,153,271 successful authentications across 16,829,696 accounts and reported 99.94 percent availability against a 99.5 percent norm.

  • Delta Works, a 43-year national flood-defence programme

    After the 1953 flood, the Netherlands built 13 Delta Works between the first project in 1954 and the completion of the Maeslant Barrier in 1997, creating a long-lived national defence system of dams, sluices and storm-surge barriers.

  • Betuweroute, a freight railway that missed its operating promise

    The Netherlands opened the Betuweroute freight railway in 2007, but the Auditor General found that state operating support in 2006–2013 reached €170 million against a €76 million maximum subsidy and required another €152 million through 2015; the line was not cost-covering and its promised environmental gain was never measured.

  • MijnOverheid, a shared citizen mailbox and data portal

    The Netherlands runs MijnOverheid as one portal for government mail and personal data; in 2024 it carried 103,429,342 messages through 11,015,895 accounts with reported availability of 99.99 percent against a 99 percent norm.

  • Fyra V250, a high-speed service withdrawn after a failed launch

    The V250 trains for the Netherlands–Belgium Fyra service entered operation six years late and the service was cancelled after only 40 days, leaving the intended passenger service on the HSL-Zuid unrealised and triggering a parliamentary inquiry.

  • OVpay, nationwide contactless transit payments

    Translink and the Dutch public-transport operators rolled out OVpay nationwide in 2023, embedding bank-card and mobile check-in across the country; in 2024 the system processed 390 million travel transactions, 15 percent of all transit transactions.

  • Omgevingswet and the Digital Environment System

    On 1 January 2024 the Netherlands put the Omgevingswet and its Digital Environment System into operation, joining municipalities, provinces, water boards and the national government behind one Omgevingsloket for rules, maps and permit applications.

  • Transantiago, an integrated transport reform with rising subsidy dependence

    Chile launched the integrated Transantiago bus–metro system in 2007; an independent 2016–19 evaluation found the state subsidy per passenger fare rose from CLP 640 per CLP 1,000 paid in 2016 to CLP 790 in 2019 even as passenger production rose 7%.

  • 4G road concessions, a national infrastructure portfolio

    By September 2024, Colombia's 4G road programme comprised 30 concessions at 86.99% aggregate progress, with 14 in operation, 13 under construction, two in pre-construction and one in early termination.

  • Reficar, a refinery modernization with a fiscal-liability finding

    A 2021 Contraloría fiscal-responsibility ruling on Colombia's Reficar modernization held COP2.945 trillion in damage after finding USD997 million in additional investments that added no value to the project.

  • GIGA School, one learning device per student

    Japan's MEXT GIGA School programme reached a one-device-per-student environment in 1,810 of 1,812 local school authorities (99.9%) by the end of fiscal 2022, with the remaining two scheduled to finish during fiscal 2023.

  • Monju, a fast-breeder programme ended before commercial operation

    Japan decided in December 2016 not to restart the Monju prototype fast-breeder reactor and moved to decommissioning after a 1995 sodium leak, a 2010 restart followed by equipment trouble and 2012 inspection failures; the approved plan targets roughly 30 years of decommissioning.

  • Invierte.pe, a national multi-year investment-management system

    Peru's Invierte.pe system tracks public investment across national, regional and local governments; by 25 July 2024 the three levels had executed S/25.939 billion of a S/67.797 billion investment budget, a reported 38.3% advance.

  • Reconstrucción con Cambios, a delayed recovery portfolio

    A 2023 Contraloría control report found the education portfolio of Peru's Reconstrucción con Cambios programme at 36.6% implementation by July 2023 against a 78% milestone expected in the earlier baseline, with the corresponding target date already expired.

  • ICE and a mostly renewable national electricity system

    Costa Rica's integrated electricity system generated 89.4% of its electricity from renewable sources in 2024, while ICE reported electrical coverage reaching 98.7% of households despite one of the country's driest years on record.

  • CCSS universal health-insurance reach

    Costa Rica's Caja Costarricense de Seguro Social reported health-insurance coverage of 92.92% of the national population in 2024, using household-survey and administrative records to include contributors, dependents, pensioners and state-covered households.

  • Metro de Quito, a cross-administration urban rail delivery

    Quito opened the first line of its metro in December 2023 after a multi-administration build, and the operator reported more than 54 million passenger trips during 2024 with uninterrupted service.

  • Panama Canal expansion and self-financing operations

    After the third set of locks opened in 2016, the Panama Canal Authority handled 9,944 deep-draft transits and 423 million tonnes of cargo in fiscal year 2024, reporting B/.4.986 billion in total revenue despite climate constraints.

  • Metro de Panamá network operations

    Panama's public metro network, inaugurated in 2014 and expanded with Line 2, transported 118,351,007 passengers in the twelve-month operating period reported in its 2024 institutional memory.

  • Mi Teleférico urban cable-car network

    Bolivia's Mi Teleférico network carried 78,715,401 passenger trips in 2024; its management report compared that result with a 97.7 million annual volume required for budget balance, or roughly 80% of the target while the system remained in service.

  • Industrial lithium carbonate plant below design capacity

    Bolivia's state lithium company doubled lithium-carbonate output to 2,064 tonnes in 2024 after its industrial plant began operating, but the Ministry of Economy reported that technical problems with evaporation ponds and the water-treatment plant kept production below the project's projected capacity of 15,000 tonnes a year.

  • Itaipú binational hydropower operations

    Itaipú supplied Paraguay's grid with 20,383 GWh in 2024, 4.5% more than in 2023, while the binational plant generated 67,089 GWh in total and continued operating after four decades of service.

  • Metrobús, an unfinished bus rapid transit project

    Paraguay's planned Asunción Metrobús corridor ended with an incomplete and unviable works package: in April 2024 the Public Prosecutor's Office said the state had paid certificates for works that did not meet the programme's purpose and alleged a G.180.03 billion patrimonial loss.

  • ARSAT-3 satellite programme suspended before launch

    Argentina's government review found that the ARSAT-3 construction programme, approved in 2015 with a 2019 launch plan, was suspended in 2016–17; the unbuilt satellite forced two later orbital-protection operations and left the original nationwide broadband objective undelivered.

  • DPWH national infrastructure delivery and transparency portal

    The Philippine Department of Public Works and Highways' live transparency portal records 209,419 completed contracts and 997 terminated contracts out of 258,645 contracts from 2016 to 2026, against ₱6.4 trillion of listed investment.

  • Bataan Nuclear Power Plant, a mothballed megaproject

    The Philippine Department of Energy's 2017 annual report describes the Bataan Nuclear Power Plant as mothballed and records its reassessment as part of a proposed national nuclear programme, after the original plant failed to become an operating power asset.

  • Trans-Sumatra toll-road programme, still short of its planned network

    Indonesia's public-works ministry reported in January 2024 that the Trans-Sumatra toll-road programme had 596 kilometres operating against a 2,749-kilometre planned network, with another 361 kilometres under construction and later phases still in planning.

  • National expressway build-out in 2024

    Vietnam's Ministry of Transport reported that seven road projects were completed and opened in 2024, bringing the national expressway network to more than 2,021 kilometres.

  • Cat Linh–Ha Dong metro, a delayed and over-budget delivery

    Vietnam's State Audit reported in 2019 that the Cat Linh–Ha Dong metro's approved investment had risen from VND8,700 billion to VND18,000 billion and that a line originally due in November 2013 was still unfinished after repeated schedule changes.

  • MRT Putrajaya Line

    Malaysia completed and opened the 57.7-kilometre MRT Putrajaya Line in two phases, with 36 operational stations serving a corridor of about two million people; full operations began on 16 March 2023.

  • Kuala Lumpur–Singapore high-speed rail, terminated before construction

    Malaysia allowed the bilateral Kuala Lumpur–Singapore high-speed rail agreement to terminate on 31 December 2020 and paid Singapore SGD102,815,576 in March 2021 for verified costs incurred on the project and for extending its suspension.

  • Hopewell elevated road-and-rail concession, and its termination

    Thailand approved Hopewell's 60-kilometre Bangkok Elevated Road and Train System concession in 1991, but work stalled at 14 percent completion for more than nine months during the 1997 property-market collapse and the government terminated the concession in spring 1998.

  • AVE high-speed rail network

    Spain expanded high-speed rail from the first Madrid–Seville line in 1992 to more than 4,000 kilometres of high-speed track by 2024; the Transport Ministry reported that the service reached 70 percent of the population.

  • Castor underground gas storage, and its closure

    Spain extinguished the Castor underground gas-storage concession in October 2014 after seismic events halted operation; the state transferred administration to Enagás and the decree recognised €1.350729 billion in compensation for the former concessionaire, with recovery structured over 30 years.

  • Ostrołęka C coal block, and its abandonment

    Poland began the 1,000-MW Ostrołęka C coal-block project in 2018 without full financing, suspended construction in 2020 and demolished the built elements in 2021; the Supreme Audit Office later found that the unfinished investment consumed more than PLN1.5 billion.

  • Nya Karolinska Solna public–private hospital project

    Stockholm delivered Nya Karolinska Solna through a 30-year public–private partnership: the official inquiry reports SEK 22.8 billion for construction and equipment, a projected SEK 57 billion total through 2040 including operation and maintenance, and an external comparison that found construction 53% more expensive per square metre than Scandinavian hospitals.

  • Barsebäck nuclear plant closure and decommissioning

    Sweden permanently shut Barsebäck 1 in 1999 and Barsebäck 2 in 2005; the national nuclear-safety report lists each reactor at 615 MWe and records the site as undergoing decommissioning, a 1,230-MWe asset retirement completed by political decision rather than construction failure.

  • New Children's Hospital cost escalation

    Ireland's New Children's Hospital project saw its approved budget rise from €1.73 billion to €2.24 billion by February 2024 after an independent review recorded €450 million of earlier escalation and weaknesses in set-up, planning, execution and governance.

  • Rural electrification and near-universal grid coverage

    Nicaragua's Ministry of Energy and Mines reported national electricity coverage of 99.575% in December 2024 after public electrification projects brought power to 732,427 homes and 3,853,005 people.

  • Gran Misión Vivienda Venezuela's five-million-home milestone

    Venezuela's Gran Misión Vivienda Venezuela reported delivery of its five-millionth home on 7 June 2024, with the programme saying that community self-construction supplied 75% of its construction in the preceding four years.

  • Plano de Recuperação e Resiliência delivery governance

    Portugal's PRR barometer recorded €21.9 billion across 121 investments and 43 reforms, with €14.43 billion paid to beneficiaries by 27 August 2026.

  • Lisbon–Madrid high-speed rail concession, formally abandoned

    Portugal's 2011 Council of Ministers formally abandoned the previous Lisbon–Madrid high-speed rail project, replacing its passenger priority with a freight connection through Sines, Lisbon, Setúbal, Poceirão and Madrid.

  • Delhi Commonwealth Games, and the cost-estimate escalation

    India and Delhi hosted the Commonwealth Games in October 2010, but the Comptroller and Auditor General recorded the total estimate rising from ₹1,200 crore in the May 2003 bid to ₹18,532.31 crore by October 2010.

  • MeerKAT radio telescope, a delivered national research facility

    South Africa's National Research Foundation and SARAO completed the 64-dish MeerKAT radio telescope in March 2018 on schedule and on budget, then began science operations as a precursor to the Square Kilometre Array.

  • CFE Telecomunicaciones e Internet para Todos

    Mexico's state telecom operator CFE Telecomunicaciones e Internet para Todos installed 113,683 free public internet sites by September 2024, reaching 81.2 percent of its stated 140,000-site 2025 goal.

  • New International Airport of Mexico, and its cancellation

    Mexico cancelled the partially built Texcoco airport after construction and contracts had begun; the government's 2019 cancellation paper estimated a 100 billion peso cancellation cost, including 60 billion pesos already spent and 40 billion in non-recoverable commitments.

  • Marmaray, the Bosphorus rail crossing

    Türkiye opened the Marmaray rail tunnel between Europe and Asia in October 2013 and the transport ministry reported 196 million passenger journeys in 2024, with 1.226 billion cumulative journeys since opening.

  • FATİH education technology infrastructure

    Türkiye's Ministry of National Education reported that the FATİH project had installed 620,000 interactive classroom boards by 2023 and signed a five-year TÜRKSAT service contract covering about 2,000 schools.

  • YEKA RES-1 renewable tender, and its cancellation

    Türkiye signed the 1,000 MWe YEKA RES-1 wind contract in February 2018 and completed its factory and R&D centre in 2019, but the Energy Ministry records that the contract was cancelled under a 2024 law.

  • Gotthard Base Tunnel

    Switzerland built the 57 km Gotthard Base Tunnel under the voter-approved NEAT programme and opened it to commercial traffic on 11 December 2016, on the date set, at a final cost forecast of CHF 9.541 billion against a 1998 cost basis of CHF 6.323 billion, both in 1998 prices.

  • Standard Gauge Railway, Mombasa to Naivasha

    Kenya Railways began building the Standard Gauge Railway in financial year 2014/15, completed the 472 km Mombasa to Nairobi Phase I in 2017, and opened the 120 km Phase 2A to Naivasha in September 2019 against a September 2017 start and an 18-month plan, about six months late; the line hauled 7.33 million tonnes of freight in 2025.

  • Canadian long-gun registry, its information system overrun and its dismantling

    Canada began registering all firearms under the 1995 Firearms Act from December 1998. The registry's first information system, CFIS I, had an initial estimate of $13 to 20 million and had cost $190 million by March 2005. Its successor CFIS II rose from $32 million to at least $87 million and was halted. In 2012 Parliament ended long-gun registration and ordered the destruction of about 7.5 million non-restricted registration records, which the RCMP deleted from CFIS in October 2012.

  • Tel Aviv light rail Red Line

    Israel's government approved the Red Line in December 2010 at an estimated NIS 10.7 billion, and NTA, the state-owned company delivering it, began the main construction works in 2015. By October 2021 the cost estimate had reached NIS 18.71 billion, about 75% above the original, and the completion date had been postponed six times, by about five years in total. The 24 km line opened in August 2023, and in December 2025 the State Comptroller put its construction cost at NIS 18.8 billion.

  • National high-speed rail network

    China's railway authorities built a high-speed rail network that the National Railway Administration put at about 47,000 km in operation in December 2024, from a programme that began in 2003; a World Bank review of the 27 lines in operation at the end of 2013 found a weighted average approved unit cost of RMB 129m per km for 350 km/h lines, which it put at no more than two-thirds of costs elsewhere.

  • Barakah Nuclear Energy Plant

    The UAE, through the Emirates Nuclear Energy Corporation and under licences from the Federal Authority for Nuclear Regulation issued from 2010, built four APR-1400 reactors at Barakah that ENEC reported in September 2024 were all in commercial operation and providing up to 25 percent of the UAE's electricity; Unit 1 entered commercial operation on 6 April 2021, about four years after the 2017 date the regulator recorded in its 2012 construction licence review.

  • Aeropuerto Internacional de Palmerola

    Honduras's Infrastructure Secretariat concessioned the Palmerola international airport to Palmerola International Airport S.A., with a USD 87.1 million reference investment. Works began on 5 December 2016 and operations on 11 December 2021, about 60 months after works began, against a 61-month contracted works period (start of operation is not necessarily completion of works).

  • El Chaparral (3 de Febrero) hydroelectric plant

    El Salvador's state hydro commission CEL financed the El Chaparral hydroelectric plant on the Torola River through a BCIE loan arranged in September 2008, with four planned years of construction, and inaugurated it as the 3 de Febrero plant on 19 October 2023 at an approximate cost of US$800 million; CEL gives the initial investment as US$207.8 million, so the final cost is about 3.8 times the initial figure, some 15 years after the 2008 loan.

  • Programa Ampliado de Inmunizaciones, and its erosion

    WHO and UNICEF estimated Venezuela's national DTP3 coverage among one-year-olds at 50 percent in 2025, down from 87 percent in 2015, and coverage has not returned above 66 percent in any year since 2017.

  • PetroCaribe-financed public investment programme, and its audited failure

    From September 2008 to September 2016, Haiti's Council of Ministers allocated PetroCaribe oil-credit revenue to 409 public projects, and the state fuel monetisation bureau BMPAD disbursed US$1,605,905,287.84 (92.4% of the revised budget), but the Superior Court of Auditors (CSCCA) found cost and schedule overruns across the audited works, including a Cap-Haïtien street rehabilitation that ran 18% over budget and took 21 months against an eight-month contract term.

  • Interstate Highway System

    Under the Federal-Aid Highway Act of 1956, the federal government and the states built the Interstate System. In nominal dollars, the estimated federal cost to complete it rose from $34 billion in the 1958 Interstate Cost Estimate to $114 billion in the final estimate of 1991.

  • Programa Nacional de la Vivienda, and its collapse

    Cuba's national housing programme, run by the Ministry of Construction under the housing policy presented in 2018 to close a deficit of 929,695 homes in ten years, completed 20,232 homes in 2022 and 5,493 in 2025, of which the state built 1,791.

  • Punta Catalina thermoelectric plant, and its cost overrun

    The Dominican state electricity holding CDEEE awarded the Punta Catalina coal plant in November 2013 and agreed a final contract price of US$1,945.0 million after the award, including the unloading port; after construction delays and a March 2020 dispute settlement with the contractor, the value carried into the plant's 2022 public trust was US$2,340.54 million, about 20 percent above the contract price.

  • Grand Paris Express

    The Société du Grand Paris, the state's public builder, renamed Société des grands projets by the law of 27 December 2023, has been building the Grand Paris Express automatic metro since works began in June 2016. The project's estimated total cost rose from 22.6 billion euros in March 2013 to 36.1 billion euros from October 2021, about 60 percent above the 2013 estimate.

  • Modjo-Hawassa expressway, World Bank-financed Lot 3

    The Ethiopian Roads Administration built the 57.4 km Batu/Zeway-Arsi Negele section (Lot 3) of the 202 km Modjo-Hawassa expressway under a project that became effective in 2015. The civil works were substantially complete by mid-2026, but only after cumulative extensions of 57 months to the project's closing date.

  • Línea Rivera rail rehabilitation, and its decay

    Uruguay's transport ministry signed a FOCEM-funded contract in November 2013 to rehabilitate 422 km of the Pintado to Rivera line within 36 months, cut the scope to the 310 km between Paso de los Toros and Rivera in January 2017, took the last provisional handover in May 2019, and by June 2025 reported the line in a degraded state with freight limited to 10 to 25 km/h against its set maximum of 40 km/h and no freight carried in recent years.

  • Gyeongbu high-speed railway (KTX), and its cost and schedule overrun

    Korea built the Seoul to Busan high-speed line planned in 1990 at 5,846.2 billion won for opening in early 1999; by 1993 the Ministry of Transportation re-estimated the cost at 12,174.3 billion won, the first phase opened in April 2004 and the whole line opened in 2010.

  • Gasoducto Sur Peruano, a terminated pipeline concession

    Peru's Gasoducto Sur Peruano concession, signed in July 2014 for a US$7.328 billion gas pipeline due in commercial operation by March 2019, stood at 37.32% overall progress against 76.49% scheduled in December 2016, according to the energy regulator Osinergmin, and the Ministry of Energy and Mines terminated the concession in January 2017 after the consortium failed to reach financial close.

  • Talara refinery modernisation, delivered late and over cost

    Petroperú's Talara Refinery Modernisation Project, begun with the May 2014 EPC contract, reached full operation in 2023 after Peru's Contraloría found its estimated investment had risen from US$1.3 billion to more than US$5 billion by October 2020, about 400%, and a cumulative schedule slippage of more than three years in the project's execution schedule, traced to the auxiliary-units contracting.

  • Program 35.000 MW power generation programme, and its schedule slip

    Indonesia's Ministry of Energy and Mineral Resources launched the 35,000 MW generation programme in May 2015 to be completed by 2019; by December 2022, 415 units with 16,596 MW, 47 percent of the programme, had reached commercial operation.

  • El Mutún steel complex, inaugurated in 2025 and found never to have operated

    Bolivia's Empresa Siderúrgica del Mutún, whose turnkey contract with Sinosteel was awarded in 2016 and whose complex the President inaugurated in February 2025, reported in its 2026 initial accountability review that the project stood at 92% physical progress against 100% accumulated financial execution, that its own supervision found the complex had never entered operation, and that it had served notice of intent to terminate the contract in January 2026.

  • Quang Trach to Pho Noi 500kV circuit-3 transmission line

    Vietnam built the 519-kilometre Quang Trach to Pho Noi 500kV circuit-3 transmission line across nine provinces after construction began on 18 January 2024, and the Government reported it in operation on 29 August 2024 'after six months of construction', meeting the Prime Minister's deadline of completion before September, at an investment of over VND22.3 trillion.

  • Coca Codo Sinclair hydroelectric plant

    Ecuador contracted the 1,500 MW Coca Codo Sinclair plant in October 2009 for USD 1,979.7 million with a 60-month term ending 5 October 2014; the plant entered commercial operation in November 2016, and a National Assembly oversight report found it had cost USD 2,712.5 million by August 2021, about 37 percent above the contract price, excluding a USD 599 million transmission line.

  • Puente Héroes del Chaco, Asunción to Chaco'i bridge

    Paraguay's Ministry of Public Works began building the Héroes del Chaco cable-stayed bridge, the first road link from Asunción to the Chaco, in 2020 on an estimated 36-month schedule; at the end of 2023 it reported 90% physical progress against 100% planned, and the bridge was inaugurated on 3 March 2024 and recorded as concluded with provisional acceptance in the 2024 balance.

  • Floating LNG import terminals of 2022

    After Russia's invasion of Ukraine the federal government chartered floating storage and regasification units, commissioned the first at Wilhelmshaven in December 2022, and by February 2023 expected to spend about 10 billion euros renting and running five units, against 2.94 billion euros of federal funding made available for four in May 2022.

  • Atucha II nuclear plant, and its 33-year build

    Argentina's state nuclear operator connected Atucha II to the grid in June 2014, almost 33 years after construction began in July 1981, and began commercial operation in May 2016, after a build halted in 1994 and restarted in 2006.

  • Vistula Spit shipping canal (Przekop Mierzei Wiślanej)

    Poland's Maritime Office in Gdynia signed the first construction contract for the Vistula Spit waterway on 4 October 2019 and opened the canal on 17 September 2022. The Supreme Audit Office found that by April 2023 the programme's value had risen 125 percent, from PLN 880 million to over PLN 1,984 million, and that its completion deadline had slipped two years to the end of 2024.

  • Israel Railways electrification and the Jerusalem express line, and their delays

    Israel Railways began electrifying the national network in 2000 and opened the electric express line to Jerusalem in September 2018, but by May 2020 only about 64 of 480 planned route kilometres were electrified, and the forecast completion date had moved from 2019, set in 2013, to the end of 2025, on an estimated cost of ILS 12.1 billion.

  • Samuel De Champlain Bridge corridor

    Infrastructure Canada delivered the Samuel De Champlain Bridge corridor in Montreal as a public-private partnership signed in 2015, opening the bridge in July 2019 against a contractual in-service date of December 1, 2018, at a total project cost the department reports as C$4.2 billion, after a C$235 million settlement in 2018 that paid for delay-recovery measures and oversized-part transport issues.

  • Hokuriku Shinkansen Kanazawa to Tsuruga extension, and its overrun

    Japan's Railway Construction, Transport and Technology Agency built the 125 km Kanazawa to Tsuruga extension of the Hokuriku Shinkansen from 2012; its authorised cost rose from 1.1858 trillion yen in 2017 to 1.6779 trillion yen after a second increase of 265.8 billion yen in March 2021, completion slipped one year to the end of fiscal 2023, and the line opened on 16 March 2024.

  • Botniabanan coastal railway

    Sweden built the Botniabanan railway between Nyland on the Ångermanälven and Umeå through the state and municipally owned company Botniabanan AB, starting construction in 1999 and opening it in August 2010, four years after the original 2006 schedule, at a final cost of almost SEK 16 billion in 2010 prices, which the national audit office calculated as 73 percent above the original estimate.

  • High Speed Two, and the cancellation of Phase 2

    The Department for Transport and HS2 Ltd began building High Speed Two in 2020. The government cancelled everything beyond Birmingham in 2023. By May 2026 the London to Birmingham railway alone was estimated at £87.7 billion to £102.7 billion, more than double the 2020 Phase 1 estimate, with services from Old Oak Common expected between 2036 and 2039 against a 2012 plan to complete the full network by 2033.

  • Crossrail, the Elizabeth line

    The Department for Transport and Transport for London built Crossrail through Crossrail Ltd from 2009. The NAO put its forecast cost at 28% above the 2010 budget of £14.8 billion and its opening at up to three and a half years past the original December 2018 date. The central section opened in 2022 and carried 257.4 million journeys between April 2025 and March 2026.

  • Dedicated Freight Corridors, Eastern and Western

    Indian Railways, through the Dedicated Freight Corridor Corporation, built two freight-only corridors approved by Cabinet in 2008 at ₹28,181 crore and reassessed in 2015 at ₹81,459 crore, and by March 2025 had commissioned 2,741 of their 2,843 route kilometres.

  • Olmeca refinery at Dos Bocas

    Pemex built the Olmeca refinery at Dos Bocas, authorized in December 2018 and fully operational from February 2025, under an authorized budget of US$15,963.0 million, 79 percent above the US$8,918.5 million Class IV estimate stated when its board authorized the FEL II phase in July 2020.

  • Inland Rail, and its consolidation at Parkes

    The Australian Government began building Inland Rail, a Melbourne to Brisbane freight railway, in 2018 through the Australian Rail Track Corporation, which passed delivery to its subsidiary Inland Rail Pty Ltd in May 2024; a verification report delivered to the infrastructure department in November 2025 reported the company's estimate at completion of A$45.6 billion (P90, Target scenario, estimate current as of December 2024) with completions finalised in May 2036, and the 2026-27 Budget then consolidated the project at Parkes and returned $4.4 billion in equity.

  • Kehärata airport rail loop, and its cost overrun

    The Finnish state, with the City of Vantaa paying part of the cost, began building the Kehärata (Ring Rail Line) through Helsinki Airport in Vantaa in 2009; construction costs came in above estimate, a glycol leak found at the airport took a year to resolve and reset the schedule, passenger service began on 1 July 2015, and the construction cost finally came to 770 million euros.

  • Chixoy hydroelectric project, and its cost and time overrun

    Guatemala's state electricity institute INDE built the 300 MW Chixoy hydroelectric project under contracts signed in 1977 and 1978; after the power-tunnel lining collapsed in late 1983 it entered commercial operation in November 1985, 41 months later than originally planned, at a final cost of US$823.1 million excluding finance charges against an appraisal estimate of US$372.7 million, an increase of 120 percent.

  • Abuja-Kaduna-Zaria-Kano dual carriageway, and the termination of its 2017 contract

    Nigeria's Federal Ministry of Works awarded the rehabilitation of the Abuja-Kaduna-Zaria-Kano dual carriageway to Julius Berger on 20 December 2017 at an initial N155.7 billion with a 36-month completion period; after repeated variations and augmentations, the Federal Executive Council cut the contract sum under Section I from N797.3 billion to N740.8 billion on 23 September 2024, and the ministry issued a 14-day termination notice on 4 November 2024 after the contractor rejected the reviewed sum and stopped work.

  • Neelum-Jhelum Hydropower Project, and its shutdown

    WAPDA's subsidiary NJHPC's 969 MW Neelum-Jhelum project, under construction from January 2008 and substantially completed in 2018, had cost Rs 423,446 million by June 2023 against Rs 84,502 million in the 2002 revised PC-I, nine years late; it peaked at 4,940.67 GWh in 2020 and was forced into complete shutdown by a head race tunnel failure on 2 April 2024 (the auditor counts 1,797.704 million units lost in FY2023-24), after an earlier tail race tunnel collapse in July 2022.

  • Tarbela Fourth Extension Hydropower Project

    WAPDA built a 1,410 MW powerhouse on Tarbela Dam's fourth tunnel, effective April 2012 and commissioned in 2018; the World Bank recorded it as completed on time and below its estimated cost, with a capital cost expected at US$749 million.

  • MOSE, the Venice lagoon flood barrier

    Works on MOSE, Italy's system of 78 mobile gates at Venice's three lagoon inlets, began in 2003. All the gates were first raised on 10 July 2020, and 6,689.07 million euros had been appropriated by mid-2022 with the works about 95 percent complete and still unfinished past their planned 2021 completion.

  • Padma Multipurpose Bridge

    Bangladesh's Bridge Authority completed the 6.15 km Padma road-rail bridge with government funds. It opened to traffic on 26 June 2022 at a reported actual cost of Tk 30,770 crore, six and a half years after the 31 December 2015 completion date in the 2010 Asian Development Bank appraisal, which had costed the project at $2,915 million.

  • Noor-Ouarzazate solar complex

    Morocco's solar agency MASEN had the Noor-Ouarzazate I, II and III concentrated solar plants (510 MW) built, grid-connected and fully operational by October 2018, at a completed capital cost of US$1,962 million, about 7 percent below the appraisal estimate of US$2,093 million. Noor II and III then generated an average of 739 GWh a year in 2019 to 2023, against the 1,144 GWh expected at appraisal.

  • Pap-Angren railway and Kamchik tunnel

    Uzbekistan's government and its state railway UTY began building the 124 km Pap-Angren line with a 19 km tunnel in mid-2013 and finished the works within nine months of the World Bank loan's 2015 effectiveness, with the main infrastructure costing US$1,475.68 million against an estimate of US$1,438.75 million, about 2.6 percent over, and benefits flowing about 18 months earlier than appraisal assumed.

  • Pro-Routes high-priority road reopening and maintenance

    Between October 2008 and June 2020 the Ministry of Infrastructure's Cellule Infrastructure reopened 2,752 of a targeted 2,762 km of high-priority earth roads across five provinces and maintained 3,335 km, finishing 3.6 percent over the financing-agreement total and 28 months behind the combined original schedule.

  • Karuma Hydropower Project

    Uganda began building the 600 MW Karuma hydropower station in August 2013 against a 60-month plan. By the end of June 2023 the Auditor General reported it 54 months late at 99.9 percent physical progress, and UEGCL records commercial operation from 12 June 2024.

  • Julius Nyerere Hydropower Project

    TANESCO contracted the 2,115 MW Julius Nyerere hydropower dam on the Rufiji in December 2018 for TZS 6.56 trillion over 42 months to June 2022. The contractor completed it on 31 March 2025, and claims settled in the contractor's favour raised the cost to TZS 7.44 trillion.

  • A1 motorway, Bucharest to Nadlac

    Romania's national road administration has built the 582 km A1 motorway in sections, and construction of the sections the auditors timed began in 2009, and in November 2025 the European Court of Auditors found its latest cost estimate 11 percent below the original estimate in real terms, while one EU co-funded section had run 79 months, or 263 percent of its planned time, late.

  • South-West Roads: Western Europe-Western China corridor (CAREC 1b and 6b)

    Kazakhstan's Committee for Roads upgraded 1,281 km of the Western Europe-Western China corridor and connecting roads under a US$2.5 billion programme between 2009 and 2024, for an actual cost of US$2,468.6 million against US$2,500 million appraised, but over 15 years against a planned four and a half.

  • Reseau Ferroviaire Rapide de Tunis, lines D and E, and its overruns

    Tunisia's transport ministry and the Societe du RFR built the first two lines of the Tunis rapid rail network, about 18 km plus 28 trains, financed from December 2010; the EIB's approximate total cost for the same scheme rose from EUR 550 million at the 2009 appraisal to EUR 653 million at the 2017 appraisal, Line E opened in March 2023 and Line D on 25 January 2025, against a 2015 project study that scheduled construction of the Line E viaduct for 2014 to 2017.

  • Southern Expressway (Southern Transport Development Project)

    Sri Lanka's Road Development Authority built the country's first access-controlled expressway, about 126 km from Kottawa to Godagama. Sections I to III opened on 26 November 2011 and section IV on 15 March 2014. The project took 13 years against a planned six. Its total cost rose from US$295.9 million at the 1999 appraisal to US$906.5 million at completion in 2014, partly because it was widened from two to four lanes.

  • Melamchi Water Supply Project, and its erosion after the 2021 flood

    Nepal's government built the Melamchi River diversion tunnel and headworks to pipe an additional 170 million litres a day into the Kathmandu Valley, closing the project in June 2021, more than 14 years after its original March 2007 closing date; the 2021 flood then damaged the headworks, and water has since been diverted for about eight months a year.

  • Harare-Masvingo-Beitbridge highway rehabilitation, behind schedule

    Zimbabwe's government, funding the works from the budget, set out in its 2021 Budget to finish upgrading the roughly 580 km Harare-Beitbridge highway by 2022; it had opened 355 km to traffic by October 2022, and in July 2025 the Finance Ministry still reported 88 km outstanding, more than two and a half years past the 2022 target.

  • Solar powered milling plants contract, and its erosion

    Zambia's government contracted Shandong Dejian Group for a fixed-price US$200 million national programme of solar powered milling plants, financed in 2016 and due 24 months after the March 2016 deposit. The Auditor General found it still incomplete at 31 March 2022, 38 months after the scheduled completion date, and found 555 of the completed plants non-functional at audit in January 2024.

  • Urban Water Supply Project (PEMU), part of the Kabala programme for Bamako

    Mali's water assets company SOMAPEP-SA built the reservoirs, transmission mains and 1,016 km of distribution networks that brought water services to 803,000 people in Bamako and six other towns, alongside the Kabala treatment plant that came into service in June 2019. Of the US$130 million approved, US$119.6 million was spent, and the project closed in December 2022 against an original closing date of December 2018.

  • Ouagadougou Water Supply Project (Ziga)

    Between 2001 and 2007, ONEA, Burkina Faso's national water utility, delivered the Ziga project through a dedicated project unit. The project built the Ziga earth dam and its transmission main to Ouagadougou, plus 56,000 subsidised connections and 400 standpipes. Eleven external financiers and the government paid US$269.37 million, 131 percent of the US$205.88 million estimated at appraisal, and the project closed on its original date of 31 December 2007.

  • Jiji and Mulembwe hydropower project

    The Government of Burundi, through REGIDESO and a World Bank project unit, built the 49.5 MW Jiji (32.5 MW) and Mulembwe (17 MW) run-of-river plants with their transmission lines and substations. The project was approved in 2014 at US$270.3 million with an original closing date of December 2019. Construction began only in February 2020, after the 2015 political crisis. The World Bank put the estimated cost at US$319.1 million in November 2024. Jiji was inaugurated in June 2025 and Mulembwe in June 2026.

  • Transport Infrastructure Investment Project (national roads, ports and the Northern Railway)

    Madagascar's road authority and transport agencies delivered road, port, airport and Northern Railway works under the Transport Infrastructure Investment Project from 2004, cutting travel time on the RN44 from 24 to 6 hours, with the closing date extended four years from 30 June 2008 to 30 June 2012 and IDA-financed costs of US$169.39 million against US$150.00 million at appraisal plus US$15.60 million of additional financing added in 2007.

  • Energy Sector Support Project (substations and distribution lines)

    Malawi's electricity utility ESCOM completed and energised all 10 substations and seven of nine planned distribution lines under the Energy Sector Support Project approved in 2011, closing on 15 October 2018 against an original closing date of 30 October 2016, having disbursed US$72.1 million of US$84.7 million.

  • Morupule B coal power station, and its underperformance

    Botswana Power Corporation built the 600 MW Morupule B coal power station under an EPC contract appraised in 2009, taking the plant over with known defects on 4 May 2014 against a target of 31 December 2013, after which it ran at a capacity factor of 52 percent from April 2015 to January 2016 against the 80 percent projected at appraisal.

  • Metolong Dam and Water Supply Programme

    Lesotho's Metolong Authority built the Metolong Dam and raw water pump station near Maseru, starting impoundment on 15 February 2014 against a contract date of 31 October 2012 and delivering 93 megalitres a day on 8 October 2014 against a contract date of 1 July 2013, with every component of the programme overrunning its cost.

  • B6 Belle Rive to Quartier Militaire road upgrade

    Mauritius's Ministry of Public Infrastructure upgraded the 12.1 km B6 Belle Rive to Quartier Militaire road under the World Bank Infrastructure Project approved in 2009, at a cost of US$33.88 million against an appraisal estimate of US$21.60 million, 157 percent of the estimate.

  • Rahad Irrigation Project, and its cost and time overrun

    Sudan's government and the Rahad Corporation (RAHCO) built the Rahad irrigation scheme, 300,000 feddans east of the Rahad River, a tributary of the Blue Nile, with a main pumping station, a siphon under the Dinder River and a barrage on the Rahad River, under credits approved in March 1973; the physical works were completed in December 1982 against a planned June 1978, at a final cost of US$395.6 million against an appraisal estimate of US$125.0 million.

  • Accra bus rapid transit under the Ghana Urban Transport Project, and its cancellation

    Ghana's Department of Urban Roads, joined in 2012 by the Ministry of Local Government and Rural Development, set out in 2007 to build Sub-Saharan Africa's first bus rapid transit corridor in Accra for an estimated US$46 million of infrastructure, but after a design review raised that estimate to US$100.7 million and counterpart funds did not arrive, the BRT was dropped in the 2014 restructuring without its 9.1 km of dedicated lanes being built, and the project closed in December 2015, 35.5 months after its original December 2012 closing date.

  • Yabayo-Gagnoa road under the Fourth Highway Project, and its cost and time overrun

    Côte d'Ivoire's Ministry of Public Works built the 70 km Yabayo-Gagnoa road and rebuilt the bridge over the N'Zi River under the Fourth Highway Project (Credit 406-IVC, approved June 1973), completing it in September 1978 against a planned June 1976, at a cost of US$24.7 million against an appraisal estimate of US$12.3 million, an overrun of 101 percent.

  • Fourth Highway Project: paving of the Mamou-Kankan and Dubreka-Kolaboui roads

    Guinea's Ministry of Transport and Public Works paved the Dubreka-Kolaboui (196.5 km) and Mamou-Kankan (401 km) national roads under the Fourth Highway Project, approved in June 1988, at a latest estimated cost of US$207 million against an appraisal estimate of US$200 million, with the IDA credit closing on 31 December 1996, three years late, and the last 94 km of Mamou-Kankan still under construction in 1997.

  • Realignment of the Congo-Ocean Railway through the Mayombe, and its overruns

    The Republic of the Congo's transport agency ATC rebuilt an 88 km section of the Brazzaville to Pointe-Noire railway through the Mayombe range, with 19 bridges, three tunnels including one of 4.6 km and 17 million m3 of earthworks, completing it in mid-1985 against an expected end of 1979 at a cost of US$399 million against an estimate of US$149 million, an overrun of 168 percent.

  • Banjul Rehabilitation Project (roads, drainage and sewage), and its delay

    The Gambia's Ministry of Transport, Works and Infrastructure contracted the US$35.7 million (D1.8 billion) Banjul roads, drainage and sewage rehabilitation in May 2019 without tender, for completion by November 2021; by August 2021 12,953 m of the 15,216 m of roads, 85 percent, were built and 63 percent of the contract price paid, the pumping and lifting stations were outstanding, and the completion date had been extended to November 2022.

  • Bissau Port Project, delivered two and a half years late

    Guinea-Bissau's port authority (JAPG) rehabilitated the old commercial wharf of Bissau Port, built river ports and ferry ramps and, with a new deepwater wharf financed in parallel by four Arab funds, completed the IDA-financed Bissau Port Project on 30 June 1990 against a planned 31 December 1987, at a final cost of US$20.0 million against an appraisal estimate of US$17.36 million.

  • Šoštanj thermal power plant unit 6 (TEŠ 6), and its cost overrun

    Slovenia's state-owned power holding HSE and its subsidiary TEŠ raised the estimated cost of the 600 MW Šoštanj unit 6 from 1,302,747 thousand euros in the August 2011 investment programme, the ceiling written into the 2012 law guaranteeing its 440 million euro EIB loan, to 1,428,457 thousand euros in the February 2014 programme, breaching the condition on which the state guarantee was given, according to the Court of Audit.

  • Rail Baltica in Latvia, and its cost and schedule overrun

    The Latvian State Audit Office found in June 2024 that the estimated construction cost of Rail Baltica's main line in Latvia had risen sevenfold since 2017 to about 8.7 billion euros, that design work due by the end of 2021 was only 54 percent complete and now planned to finish by the end of 2027, and that the Riga Central Station works contracted in 2019 at 430 million euros had risen to 565 million euros.

  • Koralmbahn Graz to Klagenfurt, opened seven years after its contracted completion date

    Austria's federal rail infrastructure company ÖBB-Infrastruktur AG forecast the Koralmbahn's total cost at 6.139 billion euros at the end of 2023, 282.4 million euros or 5 percent above the 2012 baseline, but missed both the 2018 completion date in the 2004 Koralmbahn contract and the 2023 opening date in the 2012 to 2017 framework plan, according to the Court of Audit, and the line entered passenger service on 14 December 2025.

  • Fehmarn Belt fixed link, and its cost and schedule overrun

    The European Court of Auditors found in 2020 that the Fehmarn Belt fixed link, the 18 km rail and road tunnel that Denmark finances, designs and builds through its state company Femern A/S, had an initial cost estimate of 4.4 billion euros at 2008 prices (5.0 billion at 2019 values) against a latest estimate of 7.7 billion, a 54 percent increase, and that construction planned to start in 2012 for opening in 2018 had started in 2020 with opening expected in 2028.

  • Motorway construction by the Road and Motorway Directorate, and its unit cost

    The Czech Supreme Audit Office reported in June 2026 that 41 motorway sections totalling more than 300 km were opened to traffic between 2020 and 2024, after years with almost none (no kilometre in 2014, four in 2018), but that the average cost the state paid per kilometre of motorway opened rose from nearly CZK 275 million in 2020 to CZK 505 million in 2024, an increase of nearly 84 percent.

  • Pelješac Bridge, the first stage of the road connection to South Dalmatia

    Croatia's road authority awarded the 2,440-metre Pelješac Bridge to China Road and Bridge Corporation in 2018 for HRK 2.081 billion excluding VAT with a 36-month completion deadline, works started on 31 July 2018, the last steel segment was installed by 28 July 2021, and the government expected the bridge and access roads to open in June 2022, in a project whose eligible costs of 420 million euros were 85 percent financed by an EU grant of 357 million euros.

  • Decommissioning of the Bohunice V1 nuclear power plant, and its four-year slip

    Slovakia's state decommissioning company JAVYS, which the European Court of Auditors reported in 2016 as holding the Bohunice V1 decommissioning end date at 2025 with a cost estimate of 1,239 million euros, reported in its 2025 annual report that the final decontamination and demolition contract signed on 18 December 2024 runs 60 months, putting the end of decommissioning at the end of 2029, at a total estimated cost of 1,220 million euros, with 66 decommissioning projects completed by 31 December 2025.

  • Decommissioning of the Ignalina nuclear power plant, and its delays

    The European Court of Auditors found in 2016 that Lithuania's Ignalina nuclear power plant decommissioning had pushed its end date back by a further nine years since 2011 to 2038, that the interim spent fuel storage facility was ten years behind the 2005 decommissioning plan, and that the estimated decommissioning cost had risen 15 percent from 2,930 million euros in 2011 to 3,376 million in 2015, and 67 percent since the 2010 estimate.

  • Corridor X motorway sections (E-75 and E-80)

    Serbia's state road company Koridori Srbije built 45.5 km of Corridor X motorway on the E-75 towards North Macedonia and the E-80 Dimitrovgrad bypass towards Bulgaria under a loan approved in July 2009, finishing at a total project cost of EUR316.2 million against an appraisal estimate of EUR318.2 million, but taking about 10 years from approval to full completion against a planned 6.5, with the loan closing in September 2019 instead of December 2015.

  • Road Sector Development Project on the M-03 and M-12, and its cut scope

    Ukraine's road agency Ukravtodor rehabilitated or upgraded 156.3 km of the M-03 Kyiv to Kharkiv and M-12 corridors under a US$560 million loan approved in November 2015, after slow progress led the government in 2017 to cancel US$222.2 million of the loan, dropping three M-03 bypasses and two long-term maintenance contracts, so the loan closed at US$337.8 million in September 2022, nine months after its original date.

  • M6 Minsk to Grodno transit corridor upgrade

    Belarus's Ministry of Transport and Communications widened 154 km of the M6 Minsk to Grodno highway to dual carriageway under a loan approved in December 2014, against 86 km planned, after civil works for the planned sections were awarded for less than half the estimate; the corridor component cost US$242.15 million against US$259.28 million at entry, and the loan closed in June 2022 against an original June 2020.

  • Federation Road Sector Modernization Project, and its shrunken rehabilitation scope

    The Federation of Bosnia and Herzegovina's public road company PC Roads FBH delivered 76.9 km of road works, including a 35 km upgrade of the Neum to Stolac road, under a project approved in August 2016, but rehabilitated only 41.75 km of main roads against an appraisal target of 178 km, which was cut to 42.23 km in 2021, and the closing date moved from December 2021 to September 2023.

  • Local Roads Improvement Project, and its halved scope

    Moldova's State Roads Administration upgraded 149.3 km of unpaved local roads to paved standard under a project approved in October 2015, after unit costs doubled from US$230,000 to about US$415,000 per km and contracts on 42.3 km were terminated, so a 2019 restructuring cut the target from 300 km to 150 km and the project closed in July 2023 instead of March 2021.

  • Regional and Local Roads Connectivity Project

    Albania's Albanian Development Fund rehabilitated about 70 km of regional and local roads under a US$50 million loan approved in April 2018, against 55 km planned, after civil works were awarded at up to 48 percent below estimate, with the closing date extended by 18 months to June 2024.

  • Kicevo to Ohrid motorway, and its cost and time overrun

    North Macedonia's Public Enterprise for State Roads contracted Sinohydro in November 2013 to build the 56.7 km Kicevo to Ohrid section of motorway A2 for EUR411 million by January 2018; by December 2021 five annexes had moved completion to December 2023 and raised the contract value by EUR187 million (45 percent) to EUR598 million, and the State Audit Office found works 72 percent complete by value in August 2023.

  • Budapest metro line 4, first section, and its cost and time overrun

    Hungary's State Audit Office reported in September 2010 that the first section of Budapest metro line 4, approved by the capital in September 2004 at a cost of HUF236.5 billion with a deadline of end 2009, was forecast to cost HUF370 billion, 56.4 percent more, and to open in the second half of 2013.

  • Road Infrastructure Rehabilitation Project, and its cut after the 2009 budget squeeze

    Bulgaria's Road Infrastructure Agency rehabilitated national roads under a EUR144 million project approved in June 2007, but after budget cuts in 2010 cancelled three lots on about 87 km where works had not started, reducing the length from 450 km to 307 km, and closed in June 2013, two years late, at EUR97.1 million, 67 percent of the appraisal estimate.

  • Hartha power station units 2 and 3 rehabilitation, and its halt

    Iraq's Ministry of Electricity set out in 2007 to restore 400 MW at Hartha power station units 2 and 3 by December 2010 under the Emergency Electricity Reconstruction Project, but when the project closed on 30 June 2015 no capacity had been restored, the works were about 70 percent complete, the cost estimate had risen from US$150 million to US$187.62 million with a US$98.97 million financing gap, and the contractor withdrew from the site.

  • Greater Beirut Water Supply Project (Awali to Beirut conveyor), and its unfinished delivery

    Lebanon's Council for Development and Reconstruction and the Beirut Mount Lebanon Water Establishment built most of a system to bring 250,000 cubic metres a day from the Awali to 1.2 million people in Greater Beirut, but when the World Bank loan closed on 30 April 2025, 106 months after the original June 2016 closing date, no additional water had been delivered, the 24/7 supply reached in a 20,000-customer pilot zone in 2018 had not been maintained, and component costs had risen from US$370 million at approval to US$561.7 million.

  • Amman Development Corridor (Amman Ring Road phase 1), and its overrun

    Jordan's Ministry of Public Works and Housing built the 40 km first phase of the Amman Ring Road under the Amman Development Corridor Project, whose estimated total cost rose from US$160.6 million at appraisal in 2004 to US$455.97 million in March 2013, with the road works alone rising from US$106.92 million to US$279.87 million, while the loan closing date moved from June 2009 to December 2012 and one of three sections was 65 percent complete at closing.

  • East-West Highway Corridor Improvement Project (Rikoti Pass sections)

    Georgia's Roads Department completed most civil works on the Zemo Osiauri to Chumateleti and Chumateleti to Khevi sections of the East-West Highway across the Rikoti Pass by the project's closing on 30 June 2025, four and a half years after the original loan closing date of 31 December 2020, and the government's own financing rose to US$91.03 million against US$44 million planned for the enlarged project (US$24 million at approval plus US$20 million under the 2017 additional financing).

  • North-South Road Corridor Investment Program, Tranche 1

    Armenia's Ministry of Transport, Communication and Information Technologies reconstructed about 30 km of the M1 Yerevan to Ashtarak and M2 Yerevan to Artashat roads under the first tranche of the ADB-financed North-South Road Corridor programme for an implementation cost of US$68.70 million against US$68.0 million at appraisal, but completed the project on 16 June 2016 against a planned 31 December 2013, after one round of bids was rejected and the M1 section was cut from 18.4 km to about 10 km.

  • Second National Water Supply and Sanitation Project (rayon centres), and its downsizing

    Azerbaijan's water agencies built water supply and sanitation systems in eight regional (rayon) centres under the Second National Water Supply and Sanitation Project, after a 2012 restructuring cut the scope from 21 rayons to 8 because of cost increases, while the total project cost rose from US$560 million to US$641.8 million and the loan closed on 30 June 2019 instead of 28 February 2013.

  • National Road Rehabilitation (Osh-Batken-Isfana) Project

    The Kyrgyz Ministry of Transport and Communications rehabilitated 50 km of the Osh-Batken-Isfana road corridor, against about 30 km planned at approval in 2009, for a total project cost of US$52.46 million against US$30.72 million estimated, over four years and ten months instead of three, closing on 31 December 2014 instead of 30 June 2013.

  • Tehran Sewerage Project (first phase: interceptors, trunk main and southern treatment plant)

    The Tehran Sewerage Company built interceptors, trunk mains, tunnels and a wastewater treatment plant under the first phase of the Tehran Sewerage Project at a latest estimated cost of US$359.22 million against US$341.45 million at appraisal in 2000, with the treatment works costing 189 percent of their estimate and the loan closing on 30 June 2008, two years late, before the plant and the eastern trunk main were finished.

  • Central Ring Road around Moscow (TsKAD), audited by the Accounts Chamber

    Russia's Accounts Chamber found in June 2020 that the state company Avtodor's Central Ring Road project, whose first stage was originally to be built in 2014 to 2018 and was now scheduled for 2014 to 2021, had risen in cost by 2.6 billion roubles in 2019 to 315.9 billion roubles, and that launch complexes 1 and 5 were only 49 and 61 percent complete on 1 January 2020.

  • Road Maintenance and Rehabilitation Project

    Papua New Guinea's Department of Works restored or maintained 600 km of national roads against a 640 km target under the Road Maintenance and Rehabilitation Project, closing in June 2012 five and a half years after the original December 2006 closing date, with national road works under the original loan costing US$35.62 million, 158 percent of their US$22.52 million appraisal estimate.

  • Road No. 13 South upgrading under the Third Highway Improvement Project

    Laos's Ministry of Communication, Transport, Post and Construction upgraded about 200 km of Road No. 13 between Banlak 35 and Pakse to a bituminous standard, completed in March 2002, at US$157,785 per km against an appraisal estimate of US$209,670 per km, and the project closed on its original June 2003 date at US$63.78 million against US$68.92 million appraised.

  • Second Energy Sector Project, distribution rehabilitation and the 10 MWp western solar plant

    Mongolia's Ministry of Energy and its distribution companies rehabilitated the Baganuur and Erdenet-Bulgan distribution networks and built a 10 MWp solar plant in the Western Energy System under the Second Energy Sector Project, spending US$53.35 million against a US$55.40 million appraisal estimate but closing in August 2024, 25 months after the original September 2022 closing date.

  • City Rail Link, Auckland, and its cost and time overrun

    City Rail Link Limited, owned by the Crown and Auckland Council, achieved practical completion of Auckland's 3.45 km underground City Rail Link on 30 June 2026 against a target delivery cost of NZ$5,493 million, up from a NZ$3.4 billion estimate made in 2014, and the line opened to the public on 13 September 2026, after its company had planned completion for late 2024.

  • Rogun hydropower plant

    The Government of Tajikistan resumed construction of the Soviet-era Rogun hydropower plant in 2007 from the state budget, signed the main dam contract in 2016 and commissioned two temporary units (400 MW) in 2018 and 2019. It invested about US$3.3 billion in 2007 to 2022, and in November 2024 the World Bank put the cost to complete the plant at US$6.29 billion, with construction completion moved to 2033 and full reservoir impoundment not before 2039, 63 years after construction first began in 1976.

  • Kvalitetsfonden hospital building programme (supersygehuse), and its overruns

    Denmark set up Kvalitetsfonden in 2007 to fund a new hospital structure. Through it the regions are building or rebuilding 16 hospitals with a combined investment frame of about DKK 57 billion (2023 prices). Rigsrevisionen reported in November 2023 that the programme's largest overrun, Nyt Hospital Nordsjælland, had its budget raised by DKK 2.3 billion, or 44 percent, and was expected six years later than planned.

  • Modernizace dálnice D1 (D1 motorway modernisation, Mirošovice to Kývalka)

    Czechia's Road and Motorway Directorate (ŘSD) rebuilt 160.8 km of the D1 motorway between Mirošovice and Kývalka in 20 sections from April 2013, reopening the last sections in October 2021, three years later than the 2012 schedule, with costs projected at CZK 29.844 billion including the Šmejkalka bridge against CZK 28.208 billion planned.

  • Lae Port Development Project (Lae Tidal Basin, phase 1)

    Papua New Guinea's Independent Public Business Corporation, using ADB and OPEC Fund loans, built the first phase of the Lae tidal basin, a new berth and container terminal at the port of Lae, between April 2012 and December 2014. It was about four years later than planned and cost $310.4 million, against a $154 million project at the 2007 approval.

  • Second-wave motorway concessions (Central E-65, Olympia Odos, Moreas), and their reset

    Greece procured 744 km of motorway as three PPP concessions that commenced in 2008; after works were suspended in 2011 and the contracts were renegotiated in 2013 and 2015, the European Court of Auditors found the three projects delayed by four years on average, their combined cost per km up 36 percent, from 9.1 to 12.4 million euro, and the planned road length cut to 486 km.

  • Third Highway Project: M4 Baku-Shamakhi and M3 Yenikend-Shorsulu motorways

    Azerbaijan's road administration upgraded 94 km of the M4 Baku-Shamakhi highway to a four-lane road and built 48 km of new M3 motorway under the World Bank-financed Third Highway Project, at US$2.47 million per km against US$2.96 million estimated at appraisal, with the loan closing in March 2021 instead of March 2015.

  • Belene nuclear power plant, and its cancellation

    Bulgaria's state utility NEK ordered long-lead reactor equipment for the Belene nuclear plant from Atomstroyexport in 2008. The project was cancelled before any unit was completed, and on 6 December 2016 the Ministry of Energy transferred 601,617,133 euros to NEK so it could pay the damages awarded against it in ICC arbitration case 18086/GZ/MHM.

  • Belarusian nuclear power plant (BelAES), delivered behind schedule

    Belarus started building its first nuclear power plant at Ostrovets in November 2013, a two-unit WWER-1200 plant totalling 2,400 MW. Its regulator's 2019 report scheduled unit 1 for 2019 and unit 2 for 2020. Unit 1 was commissioned in 2021 and unit 2 in October 2023, three years after the 2019 schedule.

  • Bishkek-Osh road rehabilitation, third phase

    The Kyrgyz Ministry of Transport and Communications completed the third and final phase of the Bishkek-Osh road rehabilitation in July 2007, bringing the rehabilitated length of the only internal surface connection between Bishkek and Osh to 463 km, with a 31.7 percent cost overrun on base cost items and civil works finished 33 months after the October 2004 appraisal schedule.

Every delivery under building